For the full background and discussion, please see the forum post here.
Background:
Following the Bitcoin Emmission schedule would give us a target for Y4Q1 to Y4Q4 of 1.75% of the original Eco Fund per quarter. (That's 1.75% of 23.5% of total supply)
| Geyser | Platform | Pair | Chain | % of Eco Fund |
|---|---|---|---|---|
| Splendid | Aave | aAMPL | Ethereum | 0.3 % |
| Trinity v3 | Balancer v2 | WAMPL/WETH/WBTC | Ethereum | 0.3 % |
| Beehive v4 | Uniswap v2 | ETH/AMPL | Ethereum | 0.6 % |
| Crystal | Pangolin | WAVAX/AMPL | Avalanche | 0.6 % |
| Total | 1.8% |
In order to avoid downtime which may impact liquidity providers, we should strive to deploy the next round before the current round ends. This will require some scheduling forethought.
The onchain vote can execute the payload that deposits the funds to the geysers with no intermediaries. This process takes 7 days (2 days delay + 3 day voting period + 2 day timelock).
The offchain signaling step takes 5 days (2 days delay + 3 day voting period).
So I propose aiming for the following schedule, provided there is enough agreement and sufficient delegation to proceed:
July 13th - Execute onchain proposal
June 6th - Latest time to post onchain proposal.
June 22nd - Aim to post offchain signal vote. This gives us enough time for 2 snapshots, if the first one is inconclusive. Alternatively, we could take the extra time for discussion if needed.