CIDT will deliver Polywrap Go Client
Storyboard: https://consideritdone.storiesonboard.com/m/tF_f5WAg1kO8GhBrvdXbow
Polywrap: Go Client
| Epic | User Story | Estimation |
|---|---|---|
| WebAssembly Runtime | Wasmtime integration | 10 |
| WRAP Standard | Data Types | 1 |
| WRAP Standard | URI Resolver Interface | 1 |
| WRAP Standard | MessagePack Generic Interface Support | 3 |
| Wrapper | WebAssembly Wrapper | 5 |
| URI Resolver | FileSystem | 2 |
| TOTAL SP | 22 |
Proposed Dev Team specialties, along with estimated individual time commitment and cost per Story Point (SP)
| Team Roles | Time Commitment (Hrs/SP) | Rate ($/Hr) | Cost/SP |
|---|---|---|---|
| Program Manager, Scrum Master | 1 | $120 | $120.00 |
| Tech Lead, Lead Architect | 2 | $150 | $300.00 |
| Golang Developer | 8 | $120 | $960.00 |
| Total Team 1SP Cost | $1,380.00 | ||
| Total Story Points | 22 | ||
| Total Cost | $30,360.00 |
Polywrap DAO uses Story Points (SP) to derive duration estimates for development projects. We define Baseline SP = as approximately 1 Day of Individua/Team effort.
| Target Monthly Velocity | Estimated Start | Estimated Duration |
|---|---|---|
| 20 SP/Month | 1-Nov-22 | ~1-1.5 Months |
Sponsor:
By submtting this proposal, I understand that the DAO and my sponsor will be evaluating whether my work meets the acceptance criteria. If it does not, the DAO will determine what percentage of the proposal cost to pay, if any.
I also understand that I may not begin work until it is confirmed that the Snapshot proposal has passed.
[ X ] I agree