Overview

CIDT is providing development services to support frontend implementation of the Polyfolio web3 application, Milestone 1.

Milestone 1 includes the following core epics:

  • Basic setup
  • Landing page
  • Dashboard Page
  • Asset info Page
  • Protocol Info Page
  • Network Info Page
  • Settings Page

Proposal Justification

It's necessary to implement Polyfolio front-end and integrate with web3 wraps, based on the provided UI Designs

Requested Grant

Wallet Stable Coin WRAP
cidt.eth $62,720.00 TBD

Roadmap

GitHub Project: https://github.com/orgs/polywrap/projects/7/views/1

Epic User Story Story Points (SP) Cost
Basic setup Theming 1
Basic setup App routing 1
Basic setup Data storage 1
Basic setup Localization Support 5
Landing page Header 2
Landing page Connect Wallet 2
Landing page Footer 2
Landing page Mobile menu with data from sidebar 1
Landing page Mobile search bar 1
Dashboard Page Wrapper data gathering 3
Dashboard Page Sidebar 1
Dashboard Page Main Info 1
Dashboard Page Transactions tab 3
Dashboard Page Portfolio tab 5
Asset info Page Wrapper data gathering 3
Asset info Page Main graph 3
Asset info Page Overview widget 1
Asset info Page Transactions Table 3
Protocol Info Page Wrapper data gathering 3
Protocol Info Page Vaults Table 3
Network Info Page Wrapper data gathering 2
Settings Page Profile Setup 2
TOTAL SP 49

SP Team Roles & SP Cost

Proposed Dev Team specialties, along with estimated individual time commitment and cost per Story Point (SP)

Team Roles Time Commitment Rate Cost/SP
Program Manager, Scrum Master 1h/SP $120/h $120.00
Tech Lead, Lead Architect 2h/SP $120/h $240.00
Frontend Developer 8h/SP $100/h $800.00
QA/BA Specialist 2h/SP $60/h $120.00
Total Team 1SP Cost $1,280.00

Velocity & Estimated Timeline

Polywrap DAO uses Story Points (SP) to derive duration estimates for development projects. We define Baseline SP = approximately 1 Day of Individua/Team effort.

Target Monthly Velocity Estimated Start Estimated Duration
20 SP/Month Week of Feb 21, 2022 2.5 Months

Target Monthly Velocity: 20SP/Month

Sponsor Review

Sponsor: @dOrgJelli

Terms

By submtting this proposal, I understand that the DAO and my sponsor will be evaluating whether my work meets the acceptance criteria. If it does not, the DAO will determine what percentage of the proposal cost to pay, if any.

I also understand that I may not begin work until it is confirmed that the Snapshot proposal has passed.

[ X ] I agree

Off-Chain Vote

Accept
4.29K 100%
Reject
0 0%
Download mobile app to vote

Timeline

Mar 08, 2022Proposal created
Mar 08, 2022Proposal vote started
Mar 11, 2022Proposal vote ended
Oct 10, 2024Proposal updated